Departments » Community Planning and Development » Highway SR 2 Revitalization Program

Highway SR 2 Revitalization Program

Home     Projects       News     About     Newsletter     Press    FAQ      

 
In support of the City of Airway Heights Comprehensive Plan, the Highway SR 2 Revitalization committee is dedicated to involving the community in developing a business corridor that is vibrant, appealing and pedestrian friendly for our residents, as well as our visitors that utilize it daily. 


 

Committee Meetings:  Committee meetings have been postponed temporarily. 

Join our Mailing List

 


 

14th  Ave. Landscaping Project Starts

The City has begun work on the much anticipated and delayed 14th Ave. project!  Work began in March 2008 and is projected to be completed by May.  The initial work will begin from Lundstrom to King streets with work on the section from King to Lawson streets to be follow.  This effort has been painstaking at times but as the saying goes nothing good ever comes easy.  On behalf of all the parties involved in this process the city extends its thanks. 



14th  Ave. Landscaping Plan Delayed

The City sent out requests for bids in late Summer 2007 to implement the landscape plan developed by the Revitalization committee.  Unfortunately bids came back higher than anticipated and the city rejected all bids.  The City will rebid the project in Spring 2008 due to the timeframe of getting any landscaping done before the Winter season.


 

14th Ave. Landscaping Plan (Phase I) Approved by City Council

The City of Airway Heights' City Council unanimously approved the 14th Ave. Landscaping Plan from a recommendation by the Revitalization Committee.  According to the planning schedule the project will go out for bids in early June, with bids received within a few weeks after that.  Implementation will commence in late July or early August.  To see a rendering of what this landscape plan will look like click here . 


Landscaping Plan (Phase I) Finalized

The Revitalization committee has formally finalized the Phase I Landscaping Plan for the Highway 2 Corridor.  Members have had numerous discussions on this plan and the moment has arrived for implementation.  The plan will be taken to the Airway Heights City Council this month for approval, with hopes to begin the installation by July. 




Phase I of "Conceptual" Plan--Install Landscaping north of 14th Ave.

Committee members in attendance viewed a presentation by WSDOT on the benefits of traffic roundabouts and its comparison to signalized intersections.  SPW Landscape Architects showed a 3D visualization of the corridor with proposed options for the landscaping along SR-2 and 14th Ave.  Members discussed the options and came up with suggestions and voiced their desires on what the landscaping should look like.  SPW will present a landscaping plan per instructions by committee at the next meeting. 


Master "Conceptual" City Center Plan

ALSC Architects presented a draft "conceptual" city center plan for committee review.  The purpose of the plan was to give an overall vision of what the city center and corridor could look like.  Discussion is ongoing as to the specifics of the plan however as an overall concept the plan is close to what the City's Comprehensive Plan had envisioned.  Notwithstanding, the committee agreed that the area north of 14th Ave from Lundstrom to Lawson Sts. will be developed with landscaping with a plan forthcoming at the next meeting. 


Near Final Corridor Landscape Plan

Mr. Jeff Warner of ALSC Architects submitted a revised design for the Yokes and 14th Ave. landscaping plan along the H2 corridor.  This design showed a meandering 14th Ave. continuing as a two-way street from King to Lawson St.  The road is narrowed from the current 40 ft. width to 24 ft. width.  The committee proposed enlarging this concept to encompass the area from Lundstrom to Campbell St.  Once this design is submitted at the next meeting it was agreed that this plan will be implemented in phases.  To read the minutes of this meeting click on the link below.


Corridor Landscape Design

At the January 30 committee meeting Mr. Jeff Warner of ALSC Architects presented a draft design of the committee's recommendations from a our January 9 meeting.  As proposed, this project will be the initial plan at revitalizing the corridor.  Discussion ranged from whether it was feasible to close 14th Ave in front of Yokes Supermarket or allow it to remain as a through street. 

Options Proposed -- ALSC Architects presented two initial options before the committee with hopes of finalizing a plan for implementation.  The City's comprehensive plan identifies the area around Yokes Supermarket as a potential city center. Option 2 shows what could be a city center environment with pedestrian zones, whereas Option 1 does not allow a pedestrian area.   



Corridor Block Design

The north side of the H2 corridor presented some of the most difficult problems for the city when it came to dealing with the exsiting traffic patterns and accesses.  The committee came up with some preliminary design concepts that might help plan existing and future business locations along the north side corridor.  Although these concepts are doable, albeit complex, the committee suggested that further study into these concepts be delayed until the initial 14th Ave. landscape plan is developed.


                                                                                               Meeting Minutes:

November 13, 2006 
December 12, 2006 
January 9, 2007 
January 30, 200
February 27, 2007 
March 22, 2007 
April 9, 2007 
April 30, 2007 
May 22, 2007 

Business Breakfast
Kick-Off Presentation

Presentation




 


Council Approves New Park Impact Fees
4/23/2008
Monday April 21, 2008 the City Council unanimously approves Ordinance C-677. Adopting Chapter 16.09 Park Impact Mitigation Fees.

Utility Rate Changes for 2008
1/24/2008
Some water and sewer system rates changed effective January 1, 2008.

Corrected List of Stop Sign Revisions
10/17/2007